FULL ARTICLE
McAlester News Capital
NOV. 17, 2009
By James Beaty, Senior Editor
Asphalt
which has been placed over cracks to patch up the road approaches to
Hereford Lane Bridge has now pulled apart — leaving gaps in the roadway
just a few feet from where the new bridge spans U.S. Highway 69.
Sand and gravel placed in the cracks have not resolved the problem, either.
Rain has washed out some of the filler material, leaving the cracks as deep and wide as ever.
Oklahoma
Department of Transportation Acting Division 2 Engineer Calvin Carney
acknowledged that the fix was supposed to be temporary.
He said he hopes that ODOT will get the results by this week of soil that’s being tested from the site.
Opened
to traffic in October 2008, the bridge abutments and road approaches to
the new bridge have started to separate and crack.
A portion of
one road shoulder has dropped almost two inches within a few feet of
where the bridge passes over U.S. Highway 69 — one of the most
heavily-traveled bridges in the state.
To try and determine what’s causing the problem, ODOT sent drilling crews to obtain core samples of the soil at the site.
“They are analyzing that material now in Oklahoma City,” Carney said on Monday afternoon.
Samples had been obtained by first drilling through concrete at the site and then taking soil samples every 18 inches, he said.
“We’re
looking at the material that’s under there to see what it did or it did
not do,” Carney said. He said he hopes the tests will show “what’s
happening with the ‘fill’ material.”
Prior to the Hereford Lane
Exchange project, 139 density tests were performed, according to
Carney. The tests, among other things, were to determine the moisture
content on fill material used to build up the road approaches to the
bridge, according to Carney.
“We’re looking at what happened to it,” Carney said. “It could be disbursive soil.”
Asked what he meant by the term, Carney said “It’s just like when you put water on sugar — it liquefies,” he said.
Has that happened at any other bridges around McAlester?
“I’ve
seen this in other areas,” Carney said. He said he saw a similar
problem on Highway 59, in LeFlore County. Ultimately, ODOT used
materials, including sandy soil and cement, to help fill a cavity that
had formed under the highway, according to Carney.
Shouldn’t such “disbursive soil” have been detected by testing prior to the construction of the Hereford Lane project?
“Sometimes it doesn’t appear,” Carney said. “Everything is lovely and then, things happen.”
The
News-Capital reported in June that approaches to the bridge were
dropping and crumbling, leaving those who were driving across it to
experience sudden jolts as they drove over the structure.
Following
that report, ODOT put some asphalt over a portion of the bridge
approaches, hoping to lessen the “bump” factor for drivers.
However, the deterioration has continued.
Edmond-based
TTK Construction Co. served as contractor for the bridge project,
according to ODOT. The state agency planned and contracted out work on
the $7.2 million interchange.
The Hereford Lane Exchange project
came about after there were a number of accidents at the old Hereford
Lane Intersection, which forced drivers heading from East to West
Hereford Lane to have to cross the busy U.S. Highway 69.
Included
in the project were the 240-foot long bridge and its approaches, a
service road and entry and exit ramps on the bridge’s north and south
sides.
Now, the new interchange and bridge prevents people who
are driving on East and West Hereford Lane from having to cross four
lanes of Highway 69 to get to the other side.
Carney and ODOT
still insist the bridge is safe and there’s no need to close it to
traffic — although some local residents have started by-passing it.
Some
drivers have told the News-Capital they are now sticking to the service
roads and avoiding the new bridge, concerned about its safety after
their vehicles hit the bumps in the roadway approaches.
Posted on
Tue, November 17, 2009
by Crystal Drwenski