FULL ARTICLE
by: GAVIN OFF Tulsa World Data Editor
Wednesday, November 25, 2009
11/25/2009 3:58:10 AM
At different sections of the Inner Dispersal Loop, passing motorists can almost see the road evolving.
Some portions of the highway's north leg still resemble a gravel path.
Meanwhile, portions of the highway's west leg are newly paved with 10
inches of concrete.
"It changes daily," said Jennifer Tyler, project manager for the Oklahoma Department of Transportation.
With the summer work season and more than 100 days under its
belt, the construction project on the IDL is moving along, delay-free
and on schedule.
By late February work on the loop's west leg should shift from the southbound lanes to the northbound lanes.
By late April, work on the loop's north leg should shift from the westbound lanes to the eastbound lanes.
And by early 2011, work should be complete.
"To be able to shut a major highway down is extraordinary,"
Tyler said. "If it hadn't been shut down completely, it would have
taken a lot longer to complete."
So far, the weather has cooperated with the roughly 100
workers who spend their days on the closed portions of the IDL. Even
competition for resources and manpower from other stimulus-funded
projects has failed to slow construction.
The $75 million project is 30 percent complete. The project's
contractors — Manhattan Road & Bridge Co. and Sherwood Construction
Co, — have already refurbished six of the loop's bridges, including the
ones over Charles Page Boulevard and Archer and Brady streets. They
have also finished repaving the stretch of highway running from Archer
Street to the Arkansas River.
As long as Tulsa isn't hit by a major storm, construction
during the winter should progress just as smoothly in the coming
months, Tyler said.
Since cement shouldn't be poured when temperatures are below
50 degrees, crews will likely use heaters to keep the concrete warm on
certain days, Tyler said. If temperatures are cold enough, they might
have to do the same when working with the steel rebar.
But work should proceed.
"As long as there's not a thick coat of ice over everything, it really doesn't slow down much," she said.
Once done, workers will have repaved the loop's entire north and west legs, including the surface of some 40 bridges.
But they'll complete the project in phases, with the west leg's southbound lane finished first, as outlined in the contract.
Tyler said, however, that it's hard to predict when certain
ramps or sections of the highway might be opened, since even the
slightest change in the contractor's schedule could disrupt the
project's timing.
"It's difficult to plan to far out because we don't want to give false information," she said.
Posted on
Wed, November 25, 2009
by Crystal Drwenski