'Off-Broadway' closure of I-235 moves to early February

'Off-Broadway' closure of I-235 moves to early February

OKCFox.com
by Destiny Washington
Wednesday, January 22nd 2020

OKLAHOMA CITY (KOKH) — The I-235 Off Broadway project in Oklahoma City will move its first full weekend closure of 2020 into early February.

The date has been moved due to weather concerns and to allow more time for bridge beam deliveries on site.

This cancels this weekend's planned closure of I-235.

Initially, the contractor had hoped to hang new bridge beams across I-235 between N. 36th St. and N. 63rd St. This work cannot be done with traffic on the interstate due to safety concerns.

With rain shutting down work Wednesday and possibly impacting work Thursday while the site dries out, critical preparations for the closure likely will not be completed in time... FULL ARTICLE