The City of Broken Arrow is making significant improvements to streets throughout the community.
This Broken Arrow in Motion update begins on Houston, also known as 81st Street. With the widening project from Olive to Aspen, traffic has shifted to the south side, allowing Becco Construction to install storm sewer lines and curb and gutter on the north side. This $4.6 million project is funded by the 2018 General Obligation Bond.
Continuing on Houston, the widening project from 9th Street (also known as Lynn Lane) to Old Highway 51 is moving forward. A new 12-inch water line has been installed, and temporary widening on the south side is now complete. With these steps finished, traffic is shifting to the south for storm sewer work on the north side. The dirt work has begun for permanent widening, and completion remains on track for early 2027. View the full article: BrokenArrowok.gov