Stillwater bridge under construction to take longer and cost more than expected


OKC Fox

by Miranda Vondale Foster August 26, 2022

STILLWATER, Okla. (KOKH) — A bridge under construction in Stillwater is expected to take longer than what was originally intended.

The Husband St. Bridge project will take, at minimum, a half-year longer to complete and cost approximately $500k more than originally expected.

In Sept. 2014, the City of Stillwater outsourced geotechnical and engineering services, which included investigative boring. The plan for construction was based on the bedrock elevation included in the geotechnical report.


View the full article: OKCFox.com