State Highway 100 bridge over Tenkiller Dam to close for two years starting October 6

KTUL by Laqunta Dixon

September 10th 2025


GORE, OKLA. — The U.S. Army Corps of Engineers, Tulsa District, has initiated a significant bridge replacement project that will necessitate the closure of the State Highway 100 Bridge over Tenkiller Dam starting October 6.

The bridge, which has provided safe passage across Tenkiller Ferry Lake for over 70 years, is set to be demolished and reconstructed over the next two and a half years.

Raymond Todd, project manager for the USACE, Tulsa District, said, "The bridge served its purpose for more than seven decades but has reached the end of its service life."


View the full article: KTUL.com

Recent Posts

See All
Rogers county road work continues

Claremore Progress Daily Shane Jackson August 15, 2026 Several road projects are ongoing or have been recently completed across all three Rogers County districts. In District 1, led by commissioner Da

 
 
 

Comments


Trust-Logo-Orange.png

TRANSPORTATION REVENUES USED STRICTLY FOR TRANSPORTATION

CONTACT US

P.O. Box 16112

Oklahoma City, OK 73113

FIND US ON

Membership Director

Helra Han

helrahan@gmail.com

(405) 802-8184

MAILING ADDRESS

© 2026 Restore T.R.U.S.T. All Rights Reserved.
bottom of page